Days # 47, 48 and 49. 10/31/2012-11/2/2012

Day #47, 10312012

The third and final day of “mud”

Day #48, 1112012

Vernon and his crew finished the taupe siding on the North wall and placed the teal siding on the West wall

And, Paul stopped by

Day #49, 1122012

Sanding of the walls was done.  They are “paint ready”

And, the HVAC unit was installed – the exterior unit and the interior mini-split unit.  Installation will not actually be completed until Dave the electrician gets here.  He is currently helping those suffering the after effects of hurricane Sandy.  Peace.

Inbetwixt, Scott has been working to chisel and gouge the cement floor in anticipation of inlaying sea glass!!!  Below is just an audition…

Piecefully, Pam

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s